Coutyard Repair and Renovation
Long-awaited repairs to address flooding and leaks in the Beckman Institute basement and sub-basement levels will began in Spring 2026. The courtyard has been demolished, waterproofed, and reconstructed. As of November 2026, the major repairs have been completed. Smaller-scale repairs, including surface cleaning and installation of furniture and plants, will continue during the 2026-27 academic year.
Additional project updates will be posted here as applicable. The most frequent and time-sensitive communications will be distributed via the BI listserv, beckmaninstitute[at]caltech, so please make sure you and your group members are subscribed. To subscribe to the listserv, please email Pat Anguiano and request to be added.
For general questions, including questions to be relayed to the construction team, please email Beckman Institute Administrator Ariane Helou, or Project Manager Lauvai Tufele (Caltech Planning, Design & Construction).
Overall construction timeline and plan available here.
Finally, please be aware that beginning in summer 2026, ongoing construction projects at Noyes may also cause noise and vibration impact in the BI. If you encounter issues from Noyes construction, please contact Lauvai Tufele.
Latest Updates
November 11, 2026: Courtyard access will be closed for two days, for resurfacing and power washing. No access (including through internal courtyard doors) will be permitted through the BI courtyard on November 18 and 19 while the construction team is refinishing the entire top cast of the courtyard. Please observe all signage and caution tape and do not enter.
October 23, 2026: Major construction on the Beckman Institute courtyard is now complete, and the courtyard is once again open to pedestrian traffic. The central fountain is also operational for the first time in over five years! Some minor work elements still need to be completed, including painting, cleaning, touch-up, and reinstallation of furniture and planters. This work is on hold until after President Jayawardhana's inauguration on October 29, but will continue into the first weeks of November. Updates will continue to be posted here and distributed through the BI listserv.
Future planned work includes industrial cold water shutoff on Tuesday, Nov 3, 4:00-8:00AM. Please be aware that lab sinks will be affected by this shutoff.
October 2, 2026: Power washing of the interior courtyard areas impacted by construction is scheduled for Thursday, October 8. During this work, all building windows facing the courtyard must remain closed at all times. Pinnacle has been directed to ensure their subcontractor avoids power washing any windows, as the scope is limited to cleaning the exterior courtyard surfaces from the first-floor level through the fourth-floor portion of the courtyard. The center of the courtyard will be isolated with caution tape; for your safety, please refrain from entering the restricted courtyard area while this work is underway.
September 24, 2026: PD&C will be working overtime (weekends and after hours) to complete construction by their October deadline. Please be prepared for foot traffic and moderate noise and vibrations on the following dates and times:
Saturday 09/26/26 & Sunday 09/27/26, 8am to 3pm - Saw Cutting & Rebar Installation
Wednesday 09/30/26, 8am to 5pm – Saw Cutting
Saturday 10/02/26 & Sunday 10/04/26, 8am to 3pm – Stucco Patching, Painting, Cleaning
September 17, 2026: Additional saw-cutting of the new concrete will take place on Wednesday, September 23, 8:00am-3:30pm and Wednesday, September 30, 8:00am-5:00pm. This will cause noise and vibrations.
September 10, 2026: BI has just been notified that Friday, September 11, 8:00am-3:30pm there will be saw-cutting of the newly poured concrete. This will cause noise and vibrations.
August 20, 2026: Installation of waterproofing materials is producing perceptible fumes and odors throughout the building. We are actively working with Facilities to improve the building's exhaust system to lessen the odors by end of day. However, if you feel that you are being overcome by fumes in any way, please do not remain in the building. Your health and safety is the priority here. Waterproofing installation is currently scheduled to conclude by end of day Friday, August 21.
August 10, 2026: At this stage, the contractor is using handheld demolition/scraping tools to remove the remaining sections of the old waterproofing membrane and prepare the existing concrete surface. While this work can still generate noticeable noise, it is significantly less intensive than the structural demolition that has already been completed. This surface preparation is a critical step to ensure the new concrete bonds properly and provides a clean substrate for the upcoming work.
The updated construction schedule is as follows:
August 6-7: Installation of reinforcing steel (rebar) and completion of final surface preparation.
Week of August 10: Concrete placement for the courtyard, with Twinning Special Inspection on site to observe and document the work.
Weeks of Aug 10 and Aug 17: Installation of the new waterproofing system.
Following Waterproofing: Plumbing and electrical rough-in activities for the courtyard infrastructure, including the fountain systems, after which the remaining site improvements will continue.
July 23, 2026: There will be one additional day of drilling with heavy vibration and noise on Wednesday, July 29.
July 17, 2026: There will be additional days of heavy vibration and noise, Monday July 20 - Thursday July 23, as the construction team demolishes additional concrete structures recently uncovered (see photos here).
Please be advised that additional drilling will take place in the coming weeks to install the reinforcing steel for the new waterproofing system. We are waiting to learn the exact dates and duration of this work from Facilities, and will share that information as soon as we know more.
Please also note that vibrations sometimes impact the operations of elevators in the building, as heavy vibrations can register with the elevators' seismic sensors. The southwest elevator has gone out of service at least twice so far during construction. Please be advised that there may be additional elevator outages on heavy construction days, and plan accordingly.
The most recent status update (7/17/26) is available here.
June 24, 2026: The anticipated industrial water shutoff has been scheduled for Tuesday, June 30, 4:00AM-8:00AM. This shutdown is to install an isolation valve that feeds the BI courtyard; it will affect all lab sinks and any equipment utilizing industrial cold water & industrial hot water.
Once the isolation valve has been installed, the crew will be able to complete the remainder of the heavy demolition: Tuesday, June 30 - Thursday, July 2, 7:30AM - 3:30PM each day. These three days of heavy demo are anticipated to be the last of the project, but please note they will involve serious vibration and noise disturbances, so please plan accordingly.
Construction work will be suspended Friday, July 3 for the Institute holiday. Regular construction (not heavy demo) will resume Monday, July 6.
June 15, 2026: Noise and vibration data and analysis from the first week of demolition are available here (use Caltech login to access); latest project status update is here. Heavy demolition is mostly complete, but some additional heavy demo hours will be scheduled later in June to work around the water main. A brief industrial cold water shutoff may be necessary while working around the pipes; this will be announced as far in advance as possible.
June 9, 2026: An additional day of demolition has been scheduled for Monday, June 15, 7:00AM - 5:00PM. This is to make up for a partially lost workday on 6/8 as demolition was halted to repair a broken water pipe. Our current understanding is that Monday, June 15 will be the final day of heavy demolition with intense noise and vibration. Regular construction work will begin on Tuesday, June 16, causing mild to moderate noise and vibration.
June 5, 2026: An additional day of demolition is scheduled for Saturday, June 13. There will likely be heavy vibration and noise on this date.
May 28, 2026: Renovations will begin on June 1, 2026. Construction activities will take place on weekdays only, and will be paused June 11-12 for Commencement. Anticipated timeline:
June 1-2, 7am-3pm daily: Mobilization (delivery of materials, fencing, portable restrooms)
June 3-10, 7am-5pm daily: Demolition (saw cutting and jackhammering). We strongly recommend avoiding running any sensitive experiments during working hours on these dates, due to high vibration and noise.
June 15 - Sept 30, 7am-3pm daily: Construction. We anticipate that vibrations will be minimal during this period, but you may wish to consider conducting sensitive experiments after 3pm on these dates.
Additional details in Facilities announcement here.
The sound and vibration data from the soft demo is available here.
May 5, 2026: Construction permits have been approved. Beginning May 7, vibration and noise monitors will be placed in BI ground floor, basement, and sub-basement rooms. On May 20, 9:00-11:00AM, a soft demo was conducted to obtain real-time data on construction impacts (details here).
Construction will begin within 2-3 weeks after completion of the soft demo (late May / early June).
